In a project network, the critical path is the sequence of activities which has the:________.

Respuesta :

66hello60
66hello60 66hello60
  • 03-08-2022

Answer:

The correct answer is the longest time

Answer Link

Otras preguntas

Aunt agatha says that gussie "'has lost his head over a creature." how do these words reflect her feelings for gussie? they show her concern that gussie is alwa
How much is 20lbs to kg PLS HELP!!!!!
Read the following paragraph from "Adolescence and Personality": The emotional upheaval provoked by this mandate is called the identity crisis. In order to res
the sum of three even consecutive integers if the first integer is y.a.) 3y+3. b.) 3y+6c.)3y. d.) 6
What were the six goals of the government are expressed in the preamble to the constitution?
Assume ABC DEF. If AB = 12, BC = 15, and AC = 17, what is the length of EF? A. 15 B. 17 C. Cannot be determined D. 10
What is the general name for the underlying workings of a city or community
If your budget allowed you extra money for this month, would you choose to consume, invest, or save that money? Why? Be specific!
Most individuals develop a clear understanding of their language's structure, as well as a large vocabulary, during _____.
What is 49/9 to the 1/2 power