A construction company delivered 40 loads of concrete in 5 days.

What was their rate of work?



A.




B.




C.




D.


Respuesta :

melhunt99
melhunt99 melhunt99
  • 05-11-2016
Well 40 divided by 5 is 8 and you don't have options so I would say 8 loads a day :)
Answer Link

Otras preguntas

two competing airlines create a new marketing plan, charging passengers a fixed amount and then a rate per mile flown. cheapo air: $55.75 plus $0.15 a mile disc
Which of the following describes a condition in which an individual would not hear an echo? A. An individual is standing 30 meters in front of the reflecting
Which means of particle transport is shown in Figure 7–4 above? A. diffusion B. osmosis C. facilitated diffusion D. active transport
singular form of unos cuadernos:
What would be the most reliable source to consult when creating a healthy weight loss plan
Who is Tim peak where did he come from
According to the theory of plate tectonics, volcanism, mountain building, and other _____ forces receive energy from Earth’s interior.
How can doing something for someone else help relieve stress
which word correctly completes this sentence? a álvaro ______ duelen las piernas.
in the following sentence, which word is the adjective?the cold wind blew snow and dust across the road.