Six people paint the fence and 15 hours how long would it take five workers to do the same job

Respuesta :

somaiasult2006
somaiasult2006 somaiasult2006
  • 02-01-2019
it will take 12.5 hrs for five workers to do the same job.


steps:

15 × 5 = 75

75 ÷ 6 = 12.5
Answer Link

Otras preguntas

A study investigated about 3000 meals ordered from Chipotle restaurants using the online site Grubhub. Researchers calculated the sodium content (in milligrams
Which of the following statements best describes the formation of volcanoes?
In a given country the average price of a gallon of unleaded gasoline in 1997 was $1.58 in 2010 the average price was $3.11 find and interpret the average rate
List 1 inherited trait that is ONLY based on genetics and is NOT affected by the environment in any way.
A barbar wants to set up a salon in a room measuring length of 3m by 3m .He has a simple wooden chair,3 large mirrors and one bulb . a) using the knowledge of s
Plants store _____ energy in their tissues. A mechanical B heat C light D chemical
change -23/20 into a deciamal
this is for medical detectives
1/10 + -9/10 = what in fraction form
According to the Law of Conservation of Matter, if I have an Oreo cookie that weighs 20 grams and I crush it into crumbs for a recipe, how much do the crumbs we