The project team is working to create a new Web site for the company. The Web site is the _____.
a. deliverable
b. requirement
c. stakeholder
d. milestone

Respuesta :

exceloffcity
exceloffcity exceloffcity
  • 02-11-2018

B. The requirement :/

Answer Link

Otras preguntas

what does y=-(7)/(2)x+5 look like on a graph.
5x+25=9x-7 solve for x
How did new technology benefit Portuguese exploration?​
Jenny has 2.40 deducted from her monthly allowance every time she forgets a chore
What are two specific responsibilities of the Senate?
Energy drinks such as Monster and 5 Hour Energy are used to advertise an immediate boost in energy levels upon consumption, What process is occurring more readi
A class sold tickets for a dance. Student tickets cost $2 and faculty tickets cost $2.50. A total of $450 was collected and 216 tickets were sold. How many facu
of the four pillers of gross national happiness, which one is the fundamental pillar?​
The _____ perspective on management consists of the systems, contingency, and quality-management viewpoints.
which of the following is a organic molecule